Creating task and associated subtasks when version is released

Allan Morris April 17, 2020

I want to create a task and associate subtasks to that task when using the automation for Jira addon when a version is released.

I am not aware of how to define the parent issue, the only only options I get is Current Issue or Trigger Issue.

When running the trigger with the both settings to Trigger Issue, I get the following error Issue Type is a sub task but parent issue key or id is not specified.

Basically the question is: How do I reference the task I create in the trigger in the creation of the subtask?

1 answer

1 accepted

0 votes
Answer accepted
Gikku
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 18, 2020

Hi @Allan Morris 

You can try using a branch rule as below and use the parent as 'current issue'.
I think this shouldScreen Shot 2020-04-18 at 1.17.30 PM.png work.

Allan Morris April 18, 2020

That worked perfectly....Many Thanks