I want to sum-up story estimation into epic estimation ? For example
story 1 = 2 days
story 2 = 3 days
story 3 = 1 day
Epic 1 = 6 days
Kindly help with automation or any rule
Hi @Vikas Sharma -- Welcome to the Atlassian Community!
Yes, that is possible.
I recommend looking at the example rules (or posts in the community) to doing this for story points, and then change the rule to meet your needs for summing estimates.
Here is an example rule: https://www.atlassian.com/software/jira/automation-template-library#/rule/9919294
And here is the smart value documentation so you can find the replacement values you want to use: https://support.atlassian.com/cloud-automation/docs/jira-smart-values-issues/
Kind regards,
Bill
Hi Bill,
Thank you for responding . I have tried below rules unfortunately it didn't work below are the screenshots .Kindly help with right rule.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What does not work as you expect? Please be as specific as possible and include example issues/values to clarify.
You asked about estimation (time tracking) fields. Why are you editing the Story Point field in one of the rules?
Please post images of audit log details showing the rule execution. That will provide context for what you explained above.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.