Can we sum up story estimation like 2d ,4h into epic estimation? NOT asking to sumup story points

Vikas Sharma
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 20, 2023

I want to sum-up story estimation into epic estimation ? For example

story 1 = 2 days

story 2 = 3 days 

story 3 = 1 day

Epic 1 = 6 days 

Kindly help with automation or any rule 

 

1 answer

1 vote
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 20, 2023

Hi @Vikas Sharma -- Welcome to the Atlassian Community!

Yes, that is possible.

I recommend looking at the example rules (or posts in the community) to doing this for story points, and then change the rule to meet your needs for summing estimates.

Here is an example rule: https://www.atlassian.com/software/jira/automation-template-library#/rule/9919294

And here is the smart value documentation so you can find the replacement values you want to use: https://support.atlassian.com/cloud-automation/docs/jira-smart-values-issues/

Kind regards,
Bill

Vikas Sharma
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 21, 2023

Hi Bill,

Thank you for responding . I have tried below rules unfortunately it didn't work below are the screenshots  .Kindly help with right rule.C1.pngc2.pngc3.pngc4.png

Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 21, 2023

What does not work as you expect?  Please be as specific as possible and include example issues/values to clarify.

You asked about estimation (time tracking) fields.  Why are you editing the Story Point field in one of the rules?

Please post images of audit log details showing the rule execution.  That will provide context for what you explained above.