I would like to use the roadmap feature in my project to do planning and assign timelines to the work my team is doing. I manage a Design team that is a shared resource, so we take in work from several other teams and work on their Epics.
When I assign the Epic Link to an Epic from another project it will not show on my roadmap and allow the planning I'm looking for. My temporary workaround is to re-create the Epic in my space, but then my issues aren't being tracked in the other teams Epics.
We work with 7 teams, and I want my planning to be centralized to my project board to avoid having to look between 7 other project spaces.
Is it possible to use other teams epics and still do the planning in Roadmap I'm looking for on my board?
Community moderators have prevented the ability to post new answers.
Hi @frances.close - Project Roadmaps are basic and only support issues in the same project. If you want cross-project roadmapping capability, you'll need to either upgrade to Jira Software Premium licensing which brings Advanced Roadmaps in as a feature or look into a marketplace app like Structure.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.