The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

[Big Picture] [Resource Management] Fill in original estimate and logwork to use?

Nguyen Ngoc Tram _FHM_INS_
Contributor
November 21, 2021

Hi everyone,

I was a bit confused when I first used the Resource Management feature on Big Picture.
To calculate capacity, I need to fill in an original estimate and my members must logwork?
Do I need to fill (start date - end date) or (create date-due date)?

 

Thanks,

Nguyen

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Post a new discussion

Anna-BigPicture
Atlassian Partner
November 25, 2021

Hi @Nguyen Ngoc Tram _FHM_INS_

Do you refer to Team or Individual Resource Capacity?
 
The capacity of your resources is calculated based on Workload Plans and non-working days resulting from Holiday Plans and individual Absence Plans.
 
However, the formula of Team capacity is just a sum of the individual capacities of team members.
 
Here you will find a more detailed explanation: Capacity calculation.
 
Then if you have further questions or doubts, just tag me in this thread. 