I want to insert a new INITIATIVE level in the Jira Portfolio hierarchy. This new INITIATIVE level will reside between the top-level in the hierarchy, "PROGRAM", and the next level, "EPIC". I.E. when done the new hierarchy will be PROGRAM, then INITIATIVE, then EPIC.
But I have dozens of existing EPIC issues which have parent links to the PROGRAM which they belong to. If I insert a new INITIATIVE level between EPIC and PROGRAM...
1) Will this break the existing parent links in each EPIC?
2) Will it require every new EPIC to be associated with an INITIATIVE? Or is it possible to set the parent link field in each EPIC to either an INITIATIVE or a PROGRAM?
My company is running Jira Software (Server Edition) version 7.3.9 along with Jira Portfolio 2.18.