While learning how to use Portfolio, I created a new sandbox project and Portfolio plan. In my original Portfolio plan, I have the ability to reorder Epics. In my new Portfolio plan, I do not (the numbers are greyed out). I have compared JIRA project and Portfolio plan configurations and cannot figure out why I can't get permission to reorder/reprioritize my epics in the Portfolio plan view.
It would be wonderful if Portfolio noticed things like this and via a tooltip, let the user know what permission they're missing so it can be fixed or requested by the end user.
Below, you can see the numbers greyed out and I am unable to drag them up/down to reflect priority. I can change priorities in the project itself (I made sure I have the 'Schedule' permission.)
jira_portfolio_epic_ordering.JPG
Thanks for your help!
I just got stuck with this too.
Finally figured out it is because I had sorted by a different column – you have to click the # heading to sort by priority to be able drag/drop to update the ordering.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks, i was stuck as well. this helped
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This helped me too, thank you! It's very unclear that enabling drag & drop requires sorting by the number column.