Percentage of a project done does not equal the number of tasks completed

Valerie Boudreau
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 12, 2021

The green/blue status bar says 20% complete because 2 of my 10 subtasks are complete, but my parent task is only 4% complete timewise. Timewise is what matters. Who cares if I have 49 tasks of 50 complete if the 49 complete tasks are 1 hour each and the uncompleted task is 2,000 hours. So I have 49 hours out of 2,050 hours, or 2.4% done. But JIRA tells me I'm 98% done. 

I'm highly surprised JIRA has been around so long and hasn't resolved this silliness. 

jira.png