Hi All,
I wanna maintain sprints in Kanban board or I wanna change statuses of Epics/bugs when moving it through swimlines. At the movement i can't do these things in JIRA boards.
Please let me know a solution for it?
Thanks
Two questions in one!?
Sprints are part of the Scrum process. Kanban methodology doesn't use Sprints or any sort of iterative process. In a similar vein, in JIRA Software there is no way to plan Sprints on a Kanban board. However, you can point a Kanban board to a query such as sprint = "It's over 9003" or sprint = activeSprint(). Is there a reason the Scrum board doesn't work for you?
sprint = "It's over 9003"
sprint = activeSprint()
Swimlanes indicate explicit queries that show specific issues based on a criteria you choose. There's no way for JIRA to know how you'd want to update issues between lanes. What if someone had a query like updated = 12h? Would it just change the updated date to 12 hours ago?
updated = 12h
On the swimlanes one, another example I ran into yesterday - if you have two swimlanes to drag between:
How is JIRA supposed to know how to change the data? It's possible that it could be Acme + Anvil, and that's a valid combination of data, so it's already in both lanes (althoguh JIRA will hide it in the second one because it's already in the first). Or if it should change Acme, to get it out of the first lane, does it change or drop the Acme? Change to what? Even though it's unrelated to the component?
(Yes, I am watching Road Runner cartoons)
That's a perfect example. And I should watch some Tom and Jerry.
In the kanban board it is changing the Epic or Bug Statuses when moving it across columns.
Jira allows you to use the same query for both a scrum type board and a kanban board, but will not allow you to administer sprints from a Kanban board. The best way to think about this is that a board in jira is really just a view of a query (jql) but has different interface logic.
Basically the work around is to create a board of type scrum where you can create sprint codes first and then just use your kanban board as normal. This means your issue will then be able to have a value for the sprint field on edit.In my opinion Atlassian should use the same board logic and allow a switch in the board configuration for turning things on and off, such as story points and showing epics in the tab and/or the board. Right now you need two boards just to manage this.