The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How can I reset the time remaining on a story (and its sub-tasks)?

Matthew Willis
November 18, 2019

Hi!

I mistakenly logged work on a story ticket (1-day work), which I thought I fixed by deleting the work from the story and logged it on the sub-task (1-day work). I expected this to set the remaining time to 0 days, but it actually set it to estimated 1 day (1 day completed in the sub-task), d. How can I reset the remaining time?

For reference, the green bar indicates the 1 hour logged in the sub-task. The orange bar is the estimated 1 day remaining.

time tracking.png

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Pete Singleton
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 19, 2019

Looks like the original estimate on the story isn't set?  It says "Not specified".  Set the original estimate on the Story to 0, and on the sub-task to 1d.