Issue with carry over story with sub-task charging and its burn down chart

Abhishek Pethia
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 11, 2019

Hi,

we are facing issue with incomplete user stories, we need to carry over these stories and user already charges for their sub-tasks. If we carry over these stories to next sprint, the already charged hours are also carry forwarded to new sprint. this makes wrong calculation in burn down chart of new sprint.

I hope, I'm clear with my question.

or please let me know in case of more details required.

Please help to resolve this issue.

 

1 comment

Comment

Log in or Sign up to comment
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 15, 2019

This is not a "wrong calculation".  You did not complete the story you said you would do, so it carries over into the next sprint with its full estimate.