Hi,
I'm trying to use BigPicture for to plan at a high-level if the project is deliverable.
I have a bunch of Jira tickets raised, organised by Epics.
I was thinking to use Artificial Tasks, as well as Fix Versions that I prefer, because they get synchronized on the Jira ticket itself.
Question 1 - Fix Version Synchronization:
I have the following Synchronisers on:
The Automatic Task Structure is configured in the order of Project, Epic, Version, component, subtask.
The problem is that when I update the Version and add/remove items, 'Re-synch' option doesn't pick up the changes. Moreover, when i added more features into the Fix Version, the dates of the release got randomly reset.
Any advise here?
Question 2 - Task Start-End synchronisation
When i created Jira tasks, they had no estimate. I think start and end date were populated automatically. I've created dependencies between tasks, e.g. Task A depends on Task B etc. To be that means, that task A can't be started before Task B is complete. However i can't see how i can reasonably see that reflected on the gantt Chart. I would expect red arrows to be used, but instead the dependent becomes a child... that's not right.
More to that, if i amend the duration of the task in Gantt Chart by drag-and-dropping, it doesn't reflect in the Resources section of the screen which is still using the arbitrary start/end date of the original task. And the task start-end date don't get affected either.
Question 3 - work allocation
I have about 15 team members, all of them with some special powers, and i've used Teams to specify it. Some people have more than one power, so i can assign them 50/50 or similar.
I would like to allocate teams, and occasionally individuals, to calculate my real capacity. What is the easiest and simplest way to do this, with the combination of the above?
Hello Anna,
I do have a similar issue.
We built a small demo project in Jira using hardware, firmware and mechanical components and added a version 2.0.
We created a program in BigPicture from that Jira project - we couldn't get BigPicture to display the Gantt as expected:
While another gantt plugin (which has way less options than BigPicture has) displays the project as we exprected:
How can we make BigPicture displaying the issues as childs of the components as childs of the version as a child of the project?
The structure is enabled (as well as components sync is) and in the order project -> version -> components -> tasks
Can you help us here?
Thanks and Best regards,
Nick
Hello Nick,
As I mentioned in my previous message there are some cases that structure builders are conflicting. It's not possible to create structure Version >> Component >> Task, because conflicting structure builders are enabled and your tasks will be nested under only one of the builders.
Components are subsections of a project used to group data while versions control the scope of the release. Components and versions used together will create separate branches in the task structure. Depending on the order of the structure builders, an issue once nested under one of them will not move.
Let me know if you have additional questions.
Anna of SoftwarePlant Support