user story A = 3 days
User Story B = 2 days
Epic = 5 days (both together added)
or
task A = 3days
task B = 2 days
User Story = 5 days
Welcome to the community!
I'm assuming you are using Advanced Roadmaps on Jira Cloud. In which case you can go into the "View Settings", tick the Roll-up Others and then you should see the rolled-up values in the appropriate field. See 2nd screenshot (below) where the Story points field has 36 with an arrow. The arrow represents a "rolled-up" value.