Jira Portfolio 3.0, new experience.
My team are starting to use Jira Portfolio 3.0. When we run an auto-schedule, the plan shows some teams are over capacity in certain future sprints. OK. But if we accept the suggested changes, then the same team capacity changes do not seem to persist in the plan.
This is what we see before accepting an auto-schedule:
and this what we see after:
Are we missing something?