The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Team capacity in the ongoing sprint

Svajunas
July 25, 2022

Hi,

I've noticed that when viewing ongoing sprint form the advanced roadmaps "Allocated hours" reduces every day as the remaining estimate decreases though total capacity does not change. Is this functionality as intented or I am missing something?

It might be misleading viewing it after the sprint is started, as it does not account for the remaining capacity as the sprint goes on while taking into account remaining work.

For example:
Day 1; 200/200 100% full
Day 2 160/200 80% full

capacity.PNG

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Walter Buggenhout
Community Champion
July 25, 2022

Hi @Svajunas Gaina,

Yes, I believe this works as intended. In scrum, a sprint is planned ahead and the amount of hours / story points committed to is - by the book - not supposed to change either during that sprint. If your team follows this practice and does not add additional work after the sprint was started, the commitment / capacity balance during the sprint and your long term planning should not be impacted by the fact that time progresses.

Hope this helps! 

Svajunas
July 28, 2022

I've tested functionality with test project more in depth and I realized that 117/200 is the remaining/total work added to the sprint. I thought that total was the sprint capacity.

Thanks for your answer though!