Hi,
I've noticed that when viewing ongoing sprint form the advanced roadmaps "Allocated hours" reduces every day as the remaining estimate decreases though total capacity does not change. Is this functionality as intented or I am missing something?
It might be misleading viewing it after the sprint is started, as it does not account for the remaining capacity as the sprint goes on while taking into account remaining work.
For example:
Day 1; 200/200 100% full
Day 2 160/200 80% full
Solved! Go to Solution.