The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Target Start and Target End not updating for epics

John Armenia
June 18, 2019

I have an epic that has several estimated and unestimated stories.  When I auto schedule, it fills in target dates for everything as expected.  When I put estimates on the unestimated work, it correctly brings in the timeline for the newly estimated stories.  However, the parent epics target and end dates not updated based on the new information.

 

 

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Rohan
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
June 20, 2019

Hi John,

Something to consider is that if your epic doesn't have an estimate, then the Auto-schedule will respect the start and end dates that were previously set. If child issues end up outside of the epic's start or end dates, then the epic will expand to include these new issues, but it will never shrink.

This is something we're currently working to improve.

Best Regards
The Portfolio for Jira Server team

John Armenia
June 21, 2019

Ok thanks.  As it stands right now I have to clear the target dates for all my epics before I use the auto schedule feature.