Hello all,
I am trying to build an advanced roadmap for a set of teams. I am coming up against an issue where we may have a story, and a set of sub-tasks within that story that have assignees across multiple teams. Is there a workaround for this?
Hi @Ben Weisman
It is true, when using the "Team" field, like Sprint, Sub-tasks have to have the same as their parent.
The workaround is, go up a level in the hierarchy. As in, use Epic for the stories and Story (or task or whatever) for what were the sub-tasks. As "standard" level issues can be separated from the parent and have a different team, be in a different Sprint.