Sprint length in portfolio does not match JIRA

Flemming Nielsen
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 1, 2018

I have defined my project with 2-week sprint in JIRA but when looking at the plan in Portfolio, Portfolio seems to overwrite this with a 6-week sprint length except for my currently ongoing sprint.

I read the hint to start up all the sprints in JIRA, but that really creates a mess in JIRA to make the plan look nice in Portfolio. Can't I have the best of both worlds?

1 answer

0 votes
Tyler Brown
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 1, 2018

Hey Flemming,

In your Portfolio setting make sure that it's set up as a Scrum based plan and then you should be able to set up your Sprint length to your desired 2 weeks.

This guide should be able to help: https://confluence.atlassian.com/jiraportfolioserver/scheduling-settings-715263133.html

Hope this helps,

Tyler