Hi,
I have an active sprint and 3 more future sprints created in Jira. I have the start and end dates for the active sprint and the duration is 2 weeks.
When I see these sprints in Jira Portfolio, the active sprint is showing the right dates but the future sprints are showing random dates start dates few weeks in the future but have 2 week duration.
Can someone explain why the future sprint doesnt start immediately after my current active sprint?
Best, Ravi