Hi there,
I am trying to craft a Portfolio which shows me the actual assigned issues in sprints as they in the projects, for all users.
The objective is to allow me to judge long term capacity.
I am set up as follows:
- I have 10 projects worked on by a single team of people
- Each project has identical week long sprints set up, for example, April 1, April 2, April 3, April 4
- Each of the above projects sprints contain the issues we know need to be done and we review and change weekly
I am looking to see this replicated in portfolio to allow me to quickly move and add new issues, but vitally, view capacity in say April 4 when we are in April 1.
My current Portfolio has:
- One team - the actual team working on the projects with their genuine weekly capacity to be split over ALL projects
- All projects added as BOARDS
- The team is currently not assigned to any board, as I can only assign one
My issues
1.) Portfolio is not reflecting the actual weeks that issues are scheduled
2.) Portfolio is pulling in the backlog and randomly dumping issues in weeks.
3.) I cannot alter the sprints from within Portfolio as I have not assigned a single board. Not a biggie, as its a slow process without drag and drop but would be useful
Can anyone help?
Many thanks