Hi, I am looking for a way to be able to report of historic epics, from longer than 12 months, is this possible?
Otherwise i would have to keep epics constantly open so i don't lose historic data, is that correct?
How do I find these settings?
Hi Laura,
By default, advanced roadmaps will exclude issues that were completed more than 30 days ago. In order to update this configuration, use the plan configuration -> Exclusion Rules as follows.
For more information on completed issues in advanced roadmaps, please refer: https://support.atlassian.com/jira-software-cloud/docs/how-advanced-roadmaps-handles-completed-and-resolved-issues/
Thanks,
Sachithra