The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Re-including previously excluded scope

Warren Rowe
Contributor
December 30, 2019

Hi,

How do I re-include issues that I have explicitly excluded from the scope of a plan?

On a side note, how do I see which issues that have been excluded from a plan's scope?

Regards, 

Warren

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Cristiano Mariano
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 1, 2020

Hi! How are you doing?

You can add them again going to Issue Sources section in plan configuration.

Click "Edit issue sources" and then hit Next until the "Confirm what's in scope" screen.

You select the issues you want back and hit Done.

Hope this helps!

Warren Rowe
Contributor
January 1, 2020

Thanks - exactly what I was after.

Regards,

Warren

Like Cristiano Mariano likes this