Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Portfolio excludes issues which are marked as 'done' in capacity view

1. I plan sprint in jira: all stories are estimated, one team member is assigned to a single story. In portolio (capacity view) i see 100% capacity utilization, so my plan is ok.

2. Now sprint is activated, team members start working on issues. One story is completed and marked as done.

3. When i move to portfolio assignee is ok, but now in the capacity view i see that my capacity utilization is 96% and i have resources that are underplaned.

In my opinion - the situation should not affect the free capacity when sprint is active until i dont change estimates or replan the sprint.

I think that something is wrong or my configuration is bad. What am i missing?

Scheduling options

Assignee import level: Sub-task

Maximum assignees per story: not set

All other options: on

0 answers