You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
1. I plan sprint in jira: all stories are estimated, one team member is assigned to a single story. In portolio (capacity view) i see 100% capacity utilization, so my plan is ok.
2. Now sprint is activated, team members start working on issues. One story is completed and marked as done.
3. When i move to portfolio assignee is ok, but now in the capacity view i see that my capacity utilization is 96% and i have resources that are underplaned.
In my opinion - the situation should not affect the free capacity when sprint is active until i dont change estimates or replan the sprint.
I think that something is wrong or my configuration is bad. What am i missing?
Scheduling options
Assignee import level: Sub-task
Maximum assignees per story: not set
All other options: on