Hi folks. New to portfolio so hope someone can point me to the right direction.
I have few plans in Portfolio for Jira. e.g.
- Plan-iOS : for IOS products
- Plan-Android: for Android products
- Plan-Mobile: for all mobile products (IOS/Android) and higher level view
Plan-iOS is used by their a Product Manager for his team and Plan-Mobile is used by Product Management and Development Leadership for overall schedule view.
Now, I have a initiatives and Epics scheduled in Plan-iOS. Lets say for an initiative that date is get is 1-Jan to 1-Mar. Now this same initiative from Plan-iOS is pulled into Plan-Mobile (for reporting and tracking purpose) and this shows up with different schedule dates than what is in Plan-iOS.
Why these dates are different across plans? Both plans have nothing Uncommitted. What am I missing? I looked at community questions and videos but there is no clear mention of how different plans, working off the same set of Jira projects are suppose to present the values.