Hello,
I have installed a Trial version of Portfolio New Interface (3.2).
In my roadmap, if I move an issue around, it updates the Target Start and Target End fields of the associated Jira. It does the same If I extend or shrink the expected duration of a task, but it doesn't update the time estimates of that Jira -- which is in days in my case.
Is that the expected behavior ? What is the link between logged work / remaining time / original estimates and the roadmap view?
I'm currently ending up with discrepancies as seen below:
Thanks!
JF
My name is Roi, and I'm a product manager in the team.
The target dates do not relate to the estimate field, nor the logged work / remaining time / original estimates.
If your teams are working Scrum, Target dates could be inferred by the issues' sprint assignments. I.e: If you assign an issue a future sprint (one that was created in Jira) the target dates will be updated automatically.
More info here: https://confluence.atlassian.com/jiraportfolioserver/scheduling-issues-967895238.html
I hope that helps,