Hello All,
I set up View - "Sprint capacity management" and added Target Start (17/Jan/2022) and Target (11/Feb/2022). Time estimated for 15 hours.
Task time is 4 full weeks but it is not distributing the 15 hours throughout the 4 weeks but rather that puts all the time in the first week:
Do you have any idea what am I doing wrong? Do you need more information about my Plan?
Best regards,
Szymon
Hi Curt,
I understand that in this example where it is a task and that it could be completed in a week, but the problem is that a few weeks ago JIRA was correctly distributing the hours within the time that is assigned, but this changed (I do not know the reason) and now it is presenting the error. here is another example of an affected plan where that was distributing the hours correctly (First screenshot 1.JPG) and a few days ago it is wrong (second screenshot 2.JPG)
I note the dates on the weeks have changed (7, 14, 21 etc) to (6, 13, 20), that could be the difference.
Is that a selectable/changeable setting (sorry, I've only dealt with Cloud, which doesn't have this particular functionality)
Ultimately, if you believe it has changes and that change has broken t, raise it with Atlassian.