I have created a team and given each member 37.5 hours. When I assign an epic to them for a sprint they're greyed out and the task doesn't show in the portfolio schedule. I have tried to recalculate the plan but it doesn't do anything. Some members are completely greyed out and so they have nothing assigned to them.
Why are the members greyed out even though they're not over allocated? How could I fix it?