The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)
Atlassian Team members are employees working across the company in a wide variety of roles.
September 13, 2018 edited
Hey Yen,
Thanks for the question. If I understand correctly you want to prevent the Scheduling output from calculating issues into certain fix versions - which happens when there’s free capacity in your release to add more work and you’ve issues not assigned to a release.
Unfortunately the functionality you’re looking for isn’t available for releases with a fixed end date. I suggest you vote and watch this ticket to express your interest and receive updates: https://jira.atlassian.com/browse/JPOSERVER-1575
If you don’t mind the trade-off, a workaround may be to use Releases with ‘dynamic release date’ for those management defined releases as they will not have new scope added to it. However you lose the functionality of being able to calculate the viability of the release or display a set end date - the end date will be based on the calculated end date of your explicitly selected scope.
Please let me know if you have further questions.
Cheers, Rhys | Portfolio for Jira Product Management