Hi All,
I created one project with some epics and tasks. I also create a Plan, which imports the epics and tasks from the project scrum board.
I now want to assign team members via the Plan. If i commit my changes, the assignee on the task in the project is not updated.
I always get a warning when committing my changes in the plan: "Unable to commit the item's members/issue assignee."
The setting "Issue assignee import level" = "subtask"
The setting "Commit issue assignee" = "On"