Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

JIRA Portfolio: does issue time progress affect total planned time for a team member?

Hi!

We have issues in Sprint1 in Portfolio http://prntscr.com/8thcvy

Part of them is only partly done http://prntscr.com/8thd7v

When Sprint1 will be finished, all issues that were not completed will be moved to Sprint2 (and some issues from Sprint2 will be pushed out by them to Sprint3 and so on) http://prntscr.com/8thegt

The question is: if the issue have 10 hours estimation and completed 90% in Sprint1 (9 hours is tracked as done) after moving to the next Spint2 (in our case) how much time will it "book" for a given team member (10 hours or 1 hour)?

@Martin Suntinger @Shafqat Bhuiyan Could you please help me to understand. Thank you!

2 answers

1 vote
Martin Suntinger
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Oct 24, 2015

Hi Vladimir, 

The remaining effort which will be scheduled is always exactly the estimate visible in the backlog table. For example, if an issue had 10 hours estimate and shows 90% complete, in that moment the scheduling algorithm will still take 10 hours as the estimate to be scheduled. 

The key here is that when running a plan update (Plan > Update from Date), the remaining estimates in the backlog table are adjusted, based on the progress. Thus, if you run the plan update after the first sprint, in the update dialog you should see a suggestion that reduces the 10 hours to 1 hour based on 90% progress, and then the remaining 1 hour is scheduled, from this date onwards. the plan update also adjusts the new start date of the plan, typically you'd choose the start date of the next sprint when you run the plan update. 

Hope this helps! Best, Martin

@Martin Suntinger thanks a lot. We'll experiment with it!