When evaluating the summary of hours from JIRA Portfolio the hours remaining add up to a considerable higher number than the numbers that show when I manually go into each story and add up the remaining hours. I've cleared my Cache as I believe Atlassian has said this sometimes can be an issue but if others have experienced this please advise.
Hi Kevin,
I checked internally and I could find that you raised a ticket for the support and it was answered there.
I'm posting the answer here, so others can use it.
Using example with issue
If you select the issue FPDSC-1047 estimation, you will see 81+90.
81 is the sum of all sub-tasks, 90 is the number of hours associated to the issue FPDSC-1047.
If you open the issue FPDSC-1047, you will see that this issue have no estimation in hours, but 15 story points.
Checking your plan issue source, 1 Story point = 6 hours, so the issue FPDSC-1047 have 90 hours estimated.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.