We have started to convert to using JIRA portfolio's Capacity views to track higher-level cross-team capacity for multiple engineering teams. This works great 85% of the time and the other half of the time I get into this weird invalid point calculation state where it seems to default the point totals to the capacity for the team.
In the Sprint Board Backlog View - I will see 12 issues, adding up to 48 points.
In the Portfolio Capacity View for that sprint - I will see 12 issues (correct), adding up to 55 points (incorrect)
55 is the capacity set for the team so I am assuming if it can't calculate the total - it defaults to the capacity?
Hi @matt lavinia ,
Would you be able to show a screenshot of what is happening so we can look into it. In theory the two should match.
Sometimes board filters and other factors can lead to a mismatch but this not the most likely reason.
It might also be because one of those issues has an unsaved change in Portfolio (e.g. its 1 point in Jira but 8 points in Portfolio).
Thanks,
Sam