Hi!
I am wondering if there is a way I can add some ''lead'' time in a JIRA task that can be reflected in PLAN.
Exemple:
- Task: pouring concrete takes 2 days
- lead time: concrete needs to cool down 5 days before the next task can start (walls)
How can I address this issue? Estimating 7 days of work would be innacurate.
Thank you for your help,
David