We have a SAFe programme running which has been set up using individual projects per scrum team, with a hierarchy of Capability > Feature > Story. We're using Epics to represent Features. Capability is a new issue type in JIRA. Portfolio recgnises the hierarchy and this part works fine.
We have about 10 projects and have just completed planning for our first Programme Increment. If I report on all epics and stories, the total number across the portfolio is over 2000.
Having added the projects into Portfolio, I've found that we can't drill down to user story level as Portfolio reports "The next level of hierarchy is currently disabled. There are too many issues to load them all individually. Please use the filters to narrow down the data set first"
This seems to be quite a major limitation as surely the idea of Portfolio is to bring all of the data together, and we've hit the limitation already in our first sprint!
Questions are: What is the actual limit? Any tips on getting around this? Is this configurable? Surely there is not an expectation that stories are not viewed at Portfolio level?