I have an issue A which has an estimate of 2 hours and and issue B which has an estimate of 2 hours. The team the work is connected to has enough capacity to do the work.
When I add an dependency (Issue B is depependent on Issue A), Issue B is scheduled ONE DAY LATER (visually "behind on the same level" as Issue A), although there should be enough capacity for Issue B on the day where Issue A is scheduled I would have assumed (which would mean for me a visual representaton "below" Issue A on the same day.)
Can somebody explain this behaviour? Does a dependency always mean, the issue can only be started the next day? Or what am I missing?
Thanks for your help!
Solved! Go to Solution.
Thanks @Thomas for the clarification!