Omer Farooq Chughtai September 10, 2018

I have a ticket with 5 subtasks out of which 3 are marked dev complete and the rest are in progress but developers have spent some time on them in the current sprint. When I close the sprint and the inprogress tasks are moved the the next sprint. Are the points for the closed tasks counted in the closed sprint?

Morevoer, how will the points be calculated for the in progress tasks? Will they split between the closed and the current sprint?

1 answer

0 votes
Danyal Iqbal
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 11, 2018

Are the points for the closed tasks counted in the closed sprint?

yes.

Morevoer, how will the points be calculated for the in progress tasks? Will they split between the closed and the current sprint?

No, they belong in the current sprint.

Suggest an answer