I am making changes to my team and weekly hours in JIRA Portfolio and my schedule does not change. What am I missing!?
- Scrum project/2 week iterations
- Using hours (not story points)
- I have 7 team members assigned to my project
- Only 5 team members take on actual work - at 35 hours a week
**Using the latest portfolio version
Questions
- On the Team Page: When assigning my team weekly hours - do I only add 35 hours for one week and it calculates that we are doing two week sprints? Or should I add 70 hours to account for two weeks?
- I tried to add more hours to my team work load, I added virtual team members, and it seems to not change my schedule at all. Could this be because of dependencies, we do have some?
- I also went into each individual team member under their name and added any exceptions, if they would be on Holiday or Having PTO, does the schedule take that into consideration?