In Jira Portfolio 3.x is there a way for parent issues to inherit target start/end dates?

Sophie Johnson July 1, 2019

In Jira Portfolio 3.x is there a way for parent issues to inherit target start/end dates or custom dates? I want the parent issues to take the earliest start & latest end dates and display that as their start/end.

 

Doesn't have to be Target, could be a custom field.

1 answer

1 accepted

1 vote
Answer accepted
Raathi
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
July 26, 2019

Hi Sophie,

Right now Portfolio 3.0 doesn't rollup dates to the parent issues. But we are working on a solution for this.

Regards,

Raathi

TenNineSevenSix
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 26, 2019

Hi, any update on what you are working on please?

Raathi
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
March 25, 2020

The rollup dates functionality is now available in Portfolio. You can read about it here in detail.