I am very new to JIRA portfolio
I have created a Portfolio Roadmap and was trying to figure out if there is a way to import the actual Sprints (Sprint Numbers) for each of the Feature Teams(We are using Component Field to populate Feature Team) which is assigned to a release.
I have sucessfuly imported all the Epics & Stories along with the Releases however the Sprints are displayed as Sprint 1, Sprint 2 etc and these are not the actual sprints which I want to be displayed on the Schedule
Hi, Anand
In order to import the sprints from your boards in Portfolio, in the Issue Source of your plan, you need to select the *Boards* option as source.
If you select Projects or Filters, Portfolio won't know you already have sprints created since sprints are independent on projects.
Let me know if this helps!
Gabi