We are new to Jira Cloud and I'm loving some of the new abilities to use the Roadmap feature to share progress against projects by sprints.
One issue I'm running into is I can only seem to get Incomplete Epics to show in the view pictured below. When toggling Epic display options to Complete, the image attached shows my view and is empty.
I did verify the Resolution field is populated, but is there a specific value or additional field I need to reconcile so this feature will allow me to display Done/Closed epics appropriately? Thanks!