Jay Egan July 22, 2021

We are new to Jira Cloud and I'm loving some of the new abilities to use the Roadmap feature to share progress against projects by sprints.

One issue I'm running into is I can only seem to get Incomplete Epics to show in the view pictured below. When toggling Epic display options to Complete, the image attached shows my view and is empty.

I did verify the Resolution field is populated, but is there a specific value or additional field I need to reconcile so this feature will allow me to display Done/Closed epics appropriately? Thanks!

Roadmap Question.JPG

1 answer

0 votes
Curt Holley
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 22, 2021

Hi @Jay Egan 

Welcome to the community.

I can only imagine that no Epics meet the criteria of "Complete" within the bounds of the Board's filter query.

If you take the boards filter query and adjust it to incorporate:

type = Epic and statusCategory = Done

So that you are filtering under the boards usual conditions but further filtered to show you just the completed Epics.

What do you get?

Jay Egan July 22, 2021

Thank you for the reply! I do have all of the respective epics I would see on our board, yes. Our board filter did not exclude them and I verified that by including the above as well and get this screen shot of some of the epics I recently marked as done that no longer show on the Backlog tab (expected) but are the same ones I would hope would show as Complete on the Roadmap feature.

 

Epic Status Example.JPG

Curt Holley
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 22, 2021

OK, cool. Now all you need to do is configure "Exclude any completed issues after" section so that they are back in the plan.

ex.png

Jay Egan July 23, 2021

Got it! One thing I should clarify is we do not yet have the Advanced Roadmap license. I am doing some testing on the standard version to test out if we would want to recommend upgrading. Is enabling the historical view like the above possibly a reason why I might not be able to adjust as I expected?

I will otherwise get with our admin folks and gain access to adjust as you suggest above.

Curt Holley
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 23, 2021

Yes @Jay Egan I imagine so.

The exclusion rules are in the Plans configuration. You should be able to access and set per plan.

A word with the Admins is a good idea though.

 