Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

How to Auto-schedule only some issues in Advanced Roadmaps?

This page indicates that I can just select issues under Scope, however that doesn't work. https://confluence.atlassian.com/advancedroadmapscloud/auto-scheduling-issues-998651231.html Even if I select just a single issue, the Auto-Scheduler schedules all issues in the Plan. Is there a fix or a workaround?


More broadly, my problem is the following: I have issues with estimates (in Days), and they are assigned to Releases. I'd like issues to be scheduled in order of releases, and visualize which releases will be missed (sum of estimates exceeding days remaining). Is there a better way to do this?

1 answer

Hi. I have the same issue. Have you managed to solve this?
@Misha Shemyakin 