My JIRA Portfolio project has two stages: Design and Development. These stages correspond to an issue status workflow my team is following in Kanban style. The process goes something like this:
Design
Development
The Design stage is noted as complete when issues are moved into To-do, and the Development stage is noted as complete when issues are moved into Done.
When using Portfolio's stages, there doesn't appear to be any way to map my issue statuses to stages.
So, for example, when I recalculate my plan, tasks that have already been completed in the Design phase are moved "forward" in the plan as if they still need to be completed.
Ultimately my question is how does Portfolio understand that different stages of a task are complete?
Hi Earl,
Thank you for your detailed and well though out response. I'll give changing the estimates to 0 a try to see how that works for us. Portfolio is serving a really useful purpose right now which is helping me offer clarity to people at my company when we change our product roadmap (either by adding new work, as estimates change, or as people take PTO, for example).
I'm sad to hear that stages didn't make it into the new release of Portfolio, as I feel like acknowledging that work is done in sequential, often blocking pieces is something that other timeline planning tools miss out on. Not having that seems like an over-simplification of the actual complexity that goes into planning and software development. Portfolio won me over when I saw that it took that into consideration when calculating its plan. Doing this manually would be a tedious and complicated process that Portfolio has effectively distilled down into a button click.
That being said, I'm excited to see Portfolio 3.0, it looks like you have some good changes on the horizon, and I look forward to some of those coming to JIRA Cloud.
Thank you,
Jesse