I have created a new portfolio plan. Unfortunately user stories which are already in status Done are not included in the plan. Thus any progress on epic level is incorrect.
Is there a way to include completed stories in a portfolio plan?
Community moderators have prevented the ability to post new comments.
It's on cloud.
The current cloud instance of Portfolio will only include open issues. The inclusion of closed issues has been logged as a suggestion in Atlassian's Jira: https://jira.atlassian.com/browse/JPOCLOUD-1267
Hope this helps!
Your stories are (likely) included in your plan, you just need to make them visible.
This is assuming your issue source is a board or filter based on something simple like:
project = ABC ORDER BY Rank ASC
Here are a few of things to consider:
See https://confluence.atlassian.com/jiraportfoliocloud/tracking-progress-and-status-828785247.html for more information.