The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How can I adjust the weekly capacity for individual team members

Jonas Kwaschik
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 19, 2020

Since I want to utilise advanced roadmaps for ressource planning and forecasting I need to set individual capacity for each team member, as not everyone has a standard 40 hours work week. How and where can I do that?

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Ravi Sagar _Sparxsys_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 19, 2020

Hi @Jonas Kwaschik 

Take a look at this page where you can check the limitations of the improved interface. Basically you have manage that at the team level.

Ravi

Jonas Kwaschik
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 20, 2020

Thanks Ravi, so I would basically setup a new team for each team member.