Hi!
My problem is, I have some freshly created Epics in 'New' state, with tasks what they are in 'Open' state, no hours logged in them. Despite of that, in Portfolio's Scope view, the progress bar is full. Due to this issue, the tasks under these epics cannot be scheduled. The certain task is marked with a yellpow exclamation mark in a warning sign. The error message is:
"This work item could not be scheduled because one of its parents has been marked as done. To schedule it, change the parent of this work item or change the status of the parent. Otherwise, to remove this message, mark this item as done as well."
Our Epics alway happened to be created into this state.
Can you help me?
Solved! Go to Solution.
Thank you for your help!
I have modified our 'New' state a 'To Do' type (grey) state. Now the progress bar shows actual progress, but the tasks are still not scheduled and I got the same error message.
Very interesting!
Glad it did the trick!
Please accept my response as the answer to your question so that it's seen as resolved.