Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Does Advanced Roadmaps use the working days setting to factor in non-working days?

Edited
Robert Horan
Solutions Partner
Solution Partners provide consulting, sales, and technical services on Atlassian products.
Jul 19, 2022

See https://support.atlassian.com/jira-software-cloud/docs/configure-working-days/

Does AR factor this in for capacity planning and scheduling and other planning aspects?

I've been trying to get an answer but haven't been able to find one.

Also, is there any way to put in non-working days for particular team members?  

1 answer

I've come across this challenge recently when reviewing our plans that straddle the holiday season.

From auto-scheduling the plan after putting non-working days at the end of December it doesn't appear that AR pays any attention... although it does some odd things with scheduling generally some times so an official answer would obviously be nice.

I used to use AR when it was "Portfolio" in a Server instance where you could certainly add non-working days to the plan AND non-working days on a per team member basis. Now using Cloud I certainly can't see anywhere to do this now sadly.