The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Do we have a way to compar and track against baseline in the advanced roadmaps for jira

Shubha
Contributor
June 28, 2020

Do we have a way to compare and track against baseline in the advanced roadmaps for Jira.

A tracker that can show how we are doing against the baseline plan and what items are behind schedule?

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Elad Ben-Noam
Contributor
August 4, 2020

@Shubha ,

No, there is no way to track by baseline.

If you set start/end dates to epic and issues are planned for a sprint or set issue's dates after the epic's dates you'll get a warning on the plan that the epic has issues that end after the epic.

 

I hope it helps.

Elad.

Like Júnior Zilli likes this
Dario Andres Palminio Choy
Contributor
August 24, 2021

I see that you can manage planned dates (“target start” and “target end”) and actual dates (“Start date” and “Due date”), but you cannot compare or manage “baseline”. There is no way to track by baseline.