The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Display Epics Workflow in Advanced roadmap

Sari
Contributor
February 22, 2022

Hello, 

I have a new workflow for my project (Epics): To do, Planning, Implementation, Release, Marketing, Data tracking, Done. 

I Would like to display the Epics workflow status also in the roadmap: have columns where I see these different status for each Epic in my project. 

Is this possible?

thanks!

 

 

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Chris Buzon
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 22, 2022

You can add status as a visible field, just add it to the plan columns from the little down-arrow in the Fields area.

chrome_2022-02-22_10-47-35.png

You may need to add the Epic Project as a data source (that's in configuration) if you have not already done so