Hi,
I have a project that i'm trying to use auto-schedule for. It works fine except for one Story that it skips over for some reason without warnings. This particular Story happens to have a Linked dependency that is blocking it which is assigned to a Sprint that is in a different project - could that be causing the blocked issue to be skipped? There are no warnings, which is odd. Does auto-schedule not work with Linked Issues that are in a different project's sprint? Note - I have included each project's board in my issue sources, so at least the sprints are recognized as part of the plan.