The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)
You (assuming you have the configuration right to the plan), you can go into the plan configuration UI and change the "Scheduling" option from Days to Hours for Estimation.
If you have the "Estimates (d)" field exposed in your plan, it will automatically change the name to "Estimates (h)".
Hope this helps.
Best, Joseph Chung Yin
Jira/JSM Functional Lead, Global Infrastructure Applications Team