I am pulling in sprints that are aligned to the same schedule and naming convention across different projects and boards. Aligning a single board to a single shared team. The system is successfully recognizing that the sprints of the same name from the different boards are intended to be executed in the same time period. However, the plan is shifting the sprints that were created on the board backlogs out of order, and then issuing a warning that they do not have the same dates.
I have tried to re-define the sprints, but the tool started doing strange things in the plan like creating duplicate sprints. Then instead of re-defining / renaming sprints, I deleted and started over building out the sprints. Still the same problem.
I have included attachments that show two different boards for two different teams. These teams have the same active sprint with the same start and end date. Both of these boards/teams have the same sprints built out in the same order in their backlogs. However, the plan has shifted the sprints out of order. 